How to spécify work hours per day ?
« on: January 02, 2014, 06:03:01 am »
Hi,

I'm actually testing the demo of Feng Office to switch from community to enterprise for Gantt Chart.

I do have a problem however : when I specify an estimated work time of 40 hours for a task, it appears in Gantt chart as 40 consecutive hours (a little less than 2 days), whereas we are only working 8h/day.
Gantt Chart should then display a 5 days long bar. It also seems to not take into account the non-working days (saturday and sunday).

Is this a bug or do I miss soemthing in the adminsitration tab to correct this ?

Thanks for your help,

Fred

franponce87

  • Administrator
  • Hero Member
  • *****
  • Posts: 1819
    • View Profile
    • Email
Re: How to spécify work hours per day ?
« Reply #1 on: January 02, 2014, 09:56:18 am »
Hello there!

Actually there is a way to do this: setting a start and a due date besides the task estimation time.
It will not take into account non working days yet though.

Best regards,
Francisco