Hi,
I'm actually testing the demo of Feng Office to switch from community to enterprise for Gantt Chart.
I do have a problem however : when I specify an estimated work time of 40 hours for a task, it appears in Gantt chart as 40 consecutive hours (a little less than 2 days), whereas we are only working 8h/day.
Gantt Chart should then display a 5 days long bar. It also seems to not take into account the non-working days (saturday and sunday).
Is this a bug or do I miss soemthing in the adminsitration tab to correct this ?
Thanks for your help,
Fred