Author Topic: Taks & Milestones  (Read 2439 times)

cz231

  • Newbie
  • *
  • Posts: 6
    • View Profile
Taks & Milestones
« on: December 03, 2009, 09:30:05 pm »
Hi,

I've setup a bunch of milestones and sub-tasks. However, all of a sudden, in the task tab, it only displays the milestones and no tasks. If I click on a milestone, I can see all of the tasks in that other view. However, if I add a new task, it displays under the milestone in the tasks tab. How do I show all of my subtasks under the milestone?

Thanks, and let me know if I'm unclear.

Pet

  • Global Moderator
  • Hero Member
  • *****
  • Posts: 638
  • Always mining for solutions!
    • View Profile
    • The Bet!
Re: Taks & Milestones
« Reply #1 on: December 04, 2009, 02:34:44 pm »
I can't replicate your problem. What version are you using?
Support OpenGoo - Sponsor a Feature! | Follow me on Twitter | OG Support Chat | Did you turn debugging on?

cz231

  • Newbie
  • *
  • Posts: 6
    • View Profile
Re: Taks & Milestones
« Reply #2 on: December 06, 2009, 06:50:44 pm »
The latest stable release.

Pet

  • Global Moderator
  • Hero Member
  • *****
  • Posts: 638
  • Always mining for solutions!
    • View Profile
    • The Bet!
Re: Taks & Milestones
« Reply #3 on: December 06, 2009, 07:11:09 pm »
I still can't replicate it.  What I suggest is that you review all of the filters in the top section. This is what I have, which shows milestones & subtasks:

Filter: No filter
Status: All
Group by: Milestone
Order by: Priority
Show: all 4 items