I'm often in a situation where one task (ie. design banner ad) cannot be started until another task is complete (ie. deliver assets). It would be nice to have a feature where the end date for the task Design Banner Ad is populated dynamically (from estimated time) based on the completion date of the task Deliver Assets.
Thanks!
-
+1
This is also crucial in my environment as well
Task duration should be used instead of end date (end date = start date + duration)
-
Ye... you are right..
Mee too..