: Auto Milestone Assignment To Child Tasks
: johnywhy September 10, 2009, 08:51:28 PM
a child task should automatically be assigned to the same milestone as it's parent task. that is only logical. it should be fixed, otherwise it's not a subtask.
: Re: Auto Milestone Assignment To Child Tasks
: carlos September 11, 2009, 11:25:10 AM
Hi johnywhy,

I totally agree with you, the thing is that there are many issues such as the one you mentioned which would require a redesign of the tasks module, and we haven't found the time to do it yet.

Meanwhile, if you create a subtask of another task which is currently assigned to a milestone, it will take the same milestone as a default.
: Re: Auto Milestone Assignment To Child Tasks
: johnywhy September 11, 2009, 03:47:39 PM
if you create a subtask of another task which is currently assigned to a milestone, it will take the same milestone as a default.

really? i tried that, and it did not appear to happen as you describe.
: Re: Auto Milestone Assignment To Child Tasks
: johnywhy September 14, 2009, 08:42:07 PM
it happens under certain circumstances, not others.

i believe if i add new task at the milestone screen, the milestone is auto-applied to the new task.

but if i add new task at a task screen, the milestone is not applied.